Construction and detailed design of high-pressure gas pipeline

Construction and detailed design of high-pressure gas pipeline

Preparation of the construction and detailed design together with the author's supervision for the investment task "Pogorska Wola - Tworzen Gas Pipeline"

The DN1000 8.4 MPa Pogorska Wola-Tworzen gas pipeline project with a length of approx. 168 km is an important element of the North-South gas corridor connecting the LNG terminal in Swinoujście with the planned LNG terminal in Croatia. The Pogorska Wola-Tworzen gas pipeline will also make it possible to increase Poland's energy security by unbundling the gas stream and shortening the gas fuel transport route. The gas pipeline route will pass through three voivodships - Malopolskie, Swietokrzyskie and Slaskie.

Antea Group was responsible for the design stage of the gas pipeline along with obtaining a set of administrative decisions. The scope of the contract included in particular:

  • Obtaining an environmental decision
  • Obtaining a location decision
  • Execution of the executive design
  • Execution of the construction project
  • Obtaining a building permit decision

The implementation of the investment required as four separate decisions on the building permit.

This investment is aimed at increasing the capacity of the transmission system and strengthening the security of gas transport in the region.